03
Oct
Chamwe Kaira Bannerman Energy says early construction works at the Etango uranium project are on track with both budget and schedule. The executive chairman of Bannermann Brandon Munro said detailed design work on the Etango process plant is progressing well, with dry plant engineering now about 86% complete. “I am pleased with the on-time, on-budget progress that the Bannerman team is achieving in conjunction with our contractors. Our focus on tight contract and activity controls continues to be consistently applied by the team,” Munro said. The bulk earthworks contract, awarded in August 2024 for a 24-month period, is 42% complete…
